Meeting Summary - NOGRR245 - 08/08/24 Review of Current Status

August 8, 2024

NOGRR245 Update – Slides

1 – Background of NOGRR245 - ERCOT Staff

  • ERCOT filed the original NOGRR on January 11, 2023, following NERC recommendations due to IBR failures during system disturbances.
  • IEEE 2800 was approved on February 8, 2023, leading to the NOGRR being tabled and referred to various working groups.
  • Between February and September 2023, multiple comments were filed by market participants and others.
  • On 9/14/2023, ROS granted NOGRR urgent status and recommended approval with amendments.
  • TAC tabled the NOGRR on September 27, 2023, and more comments were filed until March 2024.
  • On 3/27/2024 and 6/7/2024, TAC voted for recommending the NOGRR with various amendments from different groups.
  • Leading to 6/17/2024, joint commenters filed opposition to the TAC recommended version, threatening to appeal if approved.
  • ERCOT requested to table the NOGRR until August to address concerns of joint commenters.
  • ERCOT board tabled NOGRR245 on June 18, 2024, based on ERCOT’s request.
  • Since then, ERCOT staff worked on revisions with joint commenters to retain near-term benefits and bifurcate exemption processes.
  • Revisions aimed to clarify or obtain JC agreement, remove redundancy, correct errors, and respond to joint commenters’ concerns.
  • ERCOT plans to recommend making the subsequent bifurcation of NOGRR a board priority to be effective by April 1, 2025 to coincide with the deadline for submitting exemption requests.

Changes made to the TAC recommended version of NOGRR245:

  • Key changes include clarification that output reductions due to wind speed or solar irradiance changes are exempt from penalties during ride-through events.
  • Frequency ride-through and voltage ride-through requirements were updated.
  • Added requirement for resources to inform ERCOT on maximized ride-through capability for modeling.
  • Clarified deadlines for completing modifications and related notifications.
  • Added clarity on compliance during the fault and recovery periods.
  • Increased transparency on reporting resource maximization status to ERCOT.
  • Clarification on the exemptions or extensions for meeting new requirements and reporting responsibilities.
  • Modified information requirements for frequency and voltage ride-through capability reports.
  • Resource entities must explain efforts to verify technical limitations if unable to get OEM or consultant verification.
  • Stated that ERCOT will protect confidential information submitted in reports.
  • Specified requirements for timely submission of extension requests by April 1, 2025.

Movement to the bifurcation bucket for changes:

  • Changes made to accommodate moving exemption process criteria to a new NOGRR.
    • Section 2.6.2.1(7): Resources must submit frequency ride through capability report and request exemptions by 4/1/25. Criteria for granting exemptions will be established in the new NOGRR.
    • Section 2.12.1(1): Existing facilities not meeting ride through requirements must request an extension or exemption by 4/1/25. Criteria for exemptions to be determined in subsequent NOGRR.
    • Section 2.12.1(2): Exemption requests can only be supplemented with additional information under the new NOGRR process. No new exemption requests allowed after 4/1/25.
    • Section 2.12.1.3: Removed exemption from the title; now applies only to extensions.
    • Sections 2.12.1.3(3),(4), and (5): Removed references to exemptions, addressed in new NOGRR.
    • Sections 2.12.1.4(6) and (7): Removed references to exemptions, addressed in new NOGRR.

Bucket three corrections involved errors in the version approved by TAC:

  • 2.9.1.1(1) contained typographical errors in formulas in tables A and B.
  • 2.9.1.1(8), renumbered, corrected paragraph numbers due to a deletion and requires entities to complete maximization by 12/31.
  • 2.9.1.2(7) was renumbered to accommodate changes.
  • 2.12.1(1) corrected section references.
  • 2.12.1.4 had its title removed and subsections were renumbered as part of 2.12.1.3.

Removal of redundant or duplicative requirements in Operating Guide sections 2.9.1.1 and 2.12.1, focusing on avoiding duplication with IEEE 2800 standards:

  • Removed Table C in 2.9.1.1(1)
  • Revision and deletion of sections related to initial frequency and voltage ride-through capability reports to avoid redundancy and address objectionable language.
  • Shift in focus to discuss next steps and address questions/concerns
  • Upcoming discussions on August 19th in the R&M Committee regarding NOGRR245 and presentation of RFI results in line with NERC recommendations.
  • Board’s consideration of NOGRR245 on August 20th, aiming for approval and subsequent filing of a new NOGRR to develop exemption criteria by April 1st of next year.
  • Explanation of the process and timeline for compliance with new requirements, including potential TAC workshops to ensure expedited implementation.
  • Feedback from stakeholders indicating anticipation for the redlined version and concerns about timeline constraints in the exemption criteria update process.
  • Discussions about potential conflicts and access issues regarding IEEE 2800 standards, suggesting the need for reconsideration of including specific guidelines internally.
  • Clarification of the PGRR109 timeline for ERCOT and TSP review of dynamic models with the intent to expedite processes for ride-through capability improvements.
  • Stakeholder concerns about the practicality and timeline for meeting new requirements, with assurances of efforts to facilitate and expedite the process within allowed regulations.

3 – Description of How the Process Will Work, if Approved – ERCOT Staff

Requirement:

  • By December 31, 2025, or the synchronization date, resources under construction must meet these requirements.
  • Maximize software firmware settings and parameterization, including memory upgrades if necessary.
  • Inform ERCOT when maximized to meet or exceed section 2.6.2.1(1)-(5) and IEEE 2800, as referenced in section 2.9.1(8).
  • Report initial frequency ride through capability by April 1, 2025, if unable to maximize by the end of 2025.

Report Content:

  • The initial frequency ride through capability report must contain information outlined in section 2.11.1(1) including:
    • Resource entity’s D-U-N-S number.
    • Software firmware settings and parameterization modifications.
    • Site name
    • Description of post-modification limitations.
    • Compliance with May 1, 2024, requirements until maximization.

Voltage Ride Through Requirement:

  • For pre-8/1/24 resources, meet or exceed section 2.9.1.2(1)-(7) by 12/31/25 or the commercial operation date.
  • Submit initial report by April 1, 2025, and request extension if unable to meet requirements by the deadline.
  • Resources that meet 2.9.1.2 before 1/1/28 are exempt from IEEE 2800.

Additional Requirements: During exemption, extension, or appeal process, the resource must:

  • Meet the greater of its maximized capability or requirements in effect on 5/1.
  • Submit an implementation plan within 90 days if new software firmware setting modifications are available.
  • Notify ERCOT upon completion of maximization.
  • For resources with SGIA after 8/1/24 or undergoing significant modifications, frequency and voltage ride through standards to meet IEEE 2800 by the synchronization date.
  • Request extension if unable to comply by the deadline.

Performance Failures: If a performance failure occurs:

  • Investigate, report the cause, validate the model, and develop a mitigation plan.
  • Implement the approved plan within 180 days.
  • ERCOT may report failures to the reliability monitor if criteria are not met.

Exemption and Extension Process Highlights:

  • Requests must be submitted by 4/1/25
  • For pre-8/1/24 Resource, must accompany IFRTCR/IVRTCR
  • For Resource with approved exemption/extension, max capabilities become performance criteria until it ends.
  • Until exemption/extension/appeal is final, pre-8/1/24 AGIA Resource must meet greater of: (i) max capability, or (ii) requirements in effect on 5/1/23

Extension Timeline: Process and timeline for reviewing extension requests:

  • ERCOT confirms receipt and completeness of requests.
  • Requests additional information if needed.
  • ERCOT will try to complete the process within 180 days or provide an estimated timeline.
  • Aggrieved entities can appeal ERCOT’s decisions to the PUC under procedural rule 22.251.
  • If no appeal, entity deemed to have accepted ERCOTs decision

4 – Questions – ERCOT Staff

  • Question on repowering and replacing WTG units with type four by 4/1/27.
  • Discussion about whether criteria for type 2 sites need to be submitted; confusion over criteria definitions.
  • Issue of legacy units and facility’s reluctance to invest in modeling for SGIA signed before 8/1/2024. Need for specific answer and SME consultation recognized by ERCOT representative.
  • Replacement work will take place from March to June 2026, site offline during this period.
  • Clarification on adherence to IEEE 2800 for legacy IBR plants: must maximize capability, not just comply with minimum standards. Emphasis on maximizing equipment capabilities, not just meeting baseline requirements.
  • Discussion on performance failures and requirements for software updates and hardware changes. Importance of holistic approach to evaluate facility settings and controls ensuring voltage ride-through capability.
  • All exemption requests have to be in 4/1/25.
  • Exemptions discussion: plants need to ask by 4/1/25 if unable to meet IEEE 2800 but should be beyond 2.9.1.2.
  • Engineering concerns integrated in maximization to avoid equipment damage.
  • Meeting concluded with no further questions, slides were made available for understanding procedures.

5 – Adjourn

Get this full Meeting Summary with Clips, transcript and much more

Start your free trial today